• Freeway rehabilitation, funded by China Aid, is 55% complete and is expected to be done by October 31.
• Independence Boulevard, funded by China Aid, is 60% complete and is expected to be done by October 31.
• Wards Road and Frangipani-Hibiscus roundabouts, funded by SMPL, is 50% complete and is expected to be done by October 31.
• Ela Beach, funded through a BSP loan, is 95% complete and is expected to be done on August 15. The official opening is set for September 12.
• Stanley Esplanade, funded through BSP loan, is 60% complete and is expected to be done in early October.
• Independence Drive, funded by NCDC and GoPNG, is 50% complete and is expected to be done by October 2018.
• Magani Crescent, funded through a BSP loan, is now 99% complete and the official opening is set for next week.